Date | The date the Daily Report was created. | Required. |
Activity Note | Notes about events affecting the work on that day. | Optional. |
Today | Daily Actual Progress as a percentage, compared with Plan Progress from Input Plan. | Optional. |
Today Q. | Daily Actual Progress expressed as a quantity. | Optional. |
Remarks | Notes for each activity. | Optional. |
| Daily, weekly, and monthly charts | Cumulative progress charts for all activities or the Main Activity. | Displayed automatically. |
Safety Issue | Notes about safety issues, such as a workplace accident. | Optional. |
Engineering Issue | Notes about engineering issues. | Optional. |
Material Issue | Notes about material issues. | Optional. |
Construction Issue | Notes about construction process issues. | Optional. |
Personnel on Board | A list of personnel working that day and their positions. | Optional. |
Material & Equipment | A list of materials and equipment used that day. | Optional. |
Time & Weather | Time and weather conditions that affected the work. | Optional. |
Area of Concern & Mitigation Plan | Areas requiring attention and their mitigation plans. | Optional. |
| Other information | Additional notes for the Daily Report. | Optional. |
Prepared by | The company and PIC that prepared the Daily Report. | Optional. |
Acknowledged by | The company and PIC that reviewed or acknowledged the Daily Report. | Optional. |
Location | Work location. | Optional. |
Weather | Weather conditions on that day. | Optional. |
Event | Events recorded on that day. | Optional. |
| Photo | Photo documentation for that day. | Optional. |